UBS, 5 Broadgate
Client: UBS
Project Details:
Supply and installation of new raised access flooring to all general office areas to recently completed new build. Works included fitting out of trading floors and general office areas, installation of Main Communications Room and Sub Equipment Rooms to all floors.
RIW waterproofing works were carried out to all floors, equating to circa 5000m2 in total. 6000m2 of special area floors to Ground and First floor were installed in interlocking calcium sulphate products to take high load stone finishes. Ground floor works included an integrated heating system routered in to the surface of the panels.
Bespoke Auditorium floors were designed and installed by Connaught to provide a 150 seat tiered theatre.
Attendance was provided on all Mechanical, Electrical and Data Cabling Services installations.
Contract Duration: 12 months
Awards: Contractor of the Month | Monthly Health and Safety Award Winners | Multiple Green Card Winners